Concrete calculator

Slab, footing or post holes — get the cubic metres, the bags of pre-mix or the cement, sand and gravel to mix it yourself.

How much concrete?

Volume from the dimensions, plus a waste allowance — then ready-mix, pre-mixed bags or a site-mix materials list.

Quantities are estimates. Site-mixed concrete by volume is not a certified strength class: where a drawing, engineer or building control asks for C20/C25, GEN or RC concrete, order ready-mix to BS 8500.

Concrete mix ratios and quantities per m³

Typical site-mix quantities derived from published merchant batch figures. Densities used: cement 1,440 kg/m³ loose, sharp sand 1.6 t/m³, 20 mm gravel 1.6 t/m³, all-in ballast 2.0 t/m³.

Site-mixed concrete — materials per 1 m³ (before waste)
MixCement25 kg bagsSharp sandGravel / ballast
1 : 2 : 3 (sand : gravel)336 kg140.47 m³ / 0.75 t0.70 m³ / 1.12 t
1 : 2.5 : 3.5 (sand : gravel)288 kg120.50 m³ / 0.80 t0.70 m³ / 1.12 t
1 : 1.5 : 2.5 (sand : gravel)403 kg170.42 m³ / 0.67 t0.70 m³ / 1.12 t
1 : 3 : 6 (sand : gravel)168 kg70.35 m³ / 0.56 t0.70 m³ / 1.12 t
1 : 5 (ballast)288 kg12—1.00 m³ / 2.00 t ballast
1 : 6 (ballast)240 kg10—1.00 m³ / 2.00 t ballast
1 : 3.5 (ballast)411 kg17—1.00 m³ / 2.00 t ballast

Damp sand and ballast vary with moisture, so buy aggregates rounded up to the next half or whole cubic metre or bulk bag, and add a little extra cement.

Ready-mix designated concretes — typical uses
DesignationStrength N/mm²Typical use
GEN1 / ST210Unreinforced strip footings, trench fill, drainage
GEN3 / ST420Shed and garage bases, unreinforced floors, light domestic driveways
RC20/2525Lightly reinforced house or garage floors (ground-bearing)
RC25/3030Lightly reinforced work, reinforced foundations in non-aggressive ground
PAV1—Domestic driveways and patios exposed to frost (air-entrained)

Designated concretes for housing and general work, as ordered from a ready-mix supplier. The structural design, foundation depth and ground conditions decide what is needed.

How to work out concrete

Volume

Slab or footing: length × width × depth, all in metres. A 3 × 3 m shed base 100 mm thick is 3 × 3 × 0.1 = 0.9 m³. Post holes: π × radius² × depth for each hole, less the part of the hole the post fills.

Waste

Add an allowance for uneven ground, spillage and formwork bulging. 5–10% is a typical starting point; more on rough or hand-dug excavations.

Ready-mix, bags or site mix?

Questions groundworkers ask

How do I work out how much concrete I need?

Multiply length × width × depth in metres to get cubic metres, then add 5–10% for waste. A 3 × 3 m slab 100 mm thick is 0.9 m³, or about 1 m³ with 10% added.

How many bags of concrete make 1 m³?

About 100 bags of 20 kg ready-to-use concrete, at roughly 0.01 m³ per bag, or about 80 bags of 25 kg. Check the yield printed on the bag.

What is the mix ratio for concrete?

Common site mixes by volume are 1 : 2 : 3 (cement : sharp sand : gravel) for general work, 1 : 5 cement to all-in ballast for general purpose, and stronger mixes such as 1 : 1.5 : 2.5 for paving. They are guides, not certified strength classes.

Is a 1:2:4 or 1:5 mix the same as C20?

Not reliably. A volume-batched site mix is not tested and cannot be guaranteed to meet a strength class such as C20 or C25. If a strength or designation is specified, order ready-mix concrete to BS 8500.

More free tools for groundworkers

Aggregate calculator — Type 1, sand, gravel, topsoil — tonnes and bags› Excavation calculator — dig volume, bulking, skips and grab loads› All free calculators for the trades›

Muck, plant and money — all accounted for

Excavation inspections, plant and materials logged per job, signed dayworks, delay records and live costing.

See Graftum for groundworks
© 2026 Graftum Ltd · Software for groundworks contractors · Free calculators · Privacy
Estimates only; for a specified strength class order ready-mix to BS 8500.